How Production Order finish date and time is being comptued by SAP?

Hello Expert,

How Production Order finish date and time is being comptued by SAP? for example, we create a Production Order via CO01, the basic start date is 29.09.2008 and time is 04:00 it gives us basic finish date is 29.09.2008 and time is 13:28.

how does SAP compute the time 13:28 as it finished time

Please explain me briefly.

Thanks

Ryan

replied

Hi,

Float is defined in schedule margin key, MRP2 view of material master. you can define floats in schedule margin key through configuration.

Regards,

Dharma