Hi All
we are sending some valves bodies out for subcontracting purpose and later on packaging material to avoid the damage to valve bodies. we are sending both valve bodies and the packaging material seperately to subcontractor. While carring out the MIGO we will receive the valve boides in packaged condition. how to map this scenario in SAP.
Thanks !!!
vaibhav.....
hi
Create Finished gods material for receiving goods (after sub-contracting ).
and create semifinished material and packing material sepeartly.
Then, create BOM for finshed goods using semifinished and packing materials.
Then create sub-contract PO for finished goods-ME21N
then Transfer materials (Semifinshed and packing materials ) to kobber place.
then create sub-contract challan for the materials (Semifinished materilas)-J1IF01
then goods receipt -MIGO
If u need more details reply me ..
Thanks
sap-mm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.