Hi All

we are sending some valves bodies out for subcontracting purpose and later on packaging material to avoid the damage to valve bodies. we are sending both valve bodies and the packaging material seperately to subcontractor. While carring out the MIGO we will receive the valve boides in packaged condition. how to map this scenario in SAP.

Thanks !!!

vaibhav.....

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

Create Finished gods material for receiving goods (after sub-contracting ).

and create semifinished material and packing material sepeartly.

Then, create BOM for finshed goods using semifinished and packing materials.

Then create sub-contract PO for finished goods-ME21N

then Transfer materials (Semifinshed and packing materials ) to kobber place.

then create sub-contract challan for the materials (Semifinished materilas)-J1IF01

then goods receipt -MIGO

If u need more details reply me ..

Thanks

sap-mm

Former Member
0 Kudos

Hi

Thanks for the reply. But After MIGO I want to re use those packaging materials.

Thanks !!!

Vaibhav....