confirmation of by-product via process message

Hi All,

what are the parameters - characteristic values that needs to be passed for confirmation of the by product via process message ?

Regards,

PSS

replied

Hi,

Only the Main Product are confirmed and not the By-products.

By-products are entered in the BOM with a negative quantity. Only the main product are confirmed and Goods receipt is done by movt type 101 and the components issue is done with movt type : 261 whereas the By-products are done GR with the Movt tyoe 531.

regards

radhak mk