Pre-requiste for the confirmation of co-product by process message

Former Member
0 Kudos

Hi All,

What are the pre-requiste for the confirmation of the co-product by process message ?

I mean the characteristic values ?

Regards,

PSS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear,

You need to give PROD_* for all the products and co-products so that you can confirm indivisullay one by one.

I hope you are aware of other settings for CO-products like in material master/BOM/recipe etc.

Answers (0)