cancel
Showing results for 
Search instead for 
Did you mean: 

Controlling batch production date when using PI sheets

Former Member
0 Kudos

Hello,

The batch production date for some products is first entered at process order release. However, the GR is done using PI sheets. The GR entry via PI sheets takes the current date as the manufactured date and overwrites the old batch production date in the batch

Does anyone out there know if there is a way to control this so that old production date is not overwritten with the GR entry date?

many thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

For this you need to use the setting..Batch classification in foreground for the movement type. Do the setting in OMJJ.

Coem back after you try.