on 09-28-2008 11:19 AM
Hello All,
i have some specific questions regarding MD04 and MRP Run
1. In MD04 for few raw material i am getting -ve available quantities , i am not getting why MRP didn"t run for the same before available qty become negative , we have a batch job schedule for MRP run .
what all the possibilites of not running the MRP ,
We don't have reorder level planning ! MRP type`is standard one PD .
2. For some material we are not able to create a planned order, settings in Material Master MRP view is fine as we have another material with same settings are working , i am running the MRP through MD41 Transaction code >
Forecasting is done through MD61/62 active indicator ticked >
what else could be the reason .
Secondly one silly question does MRP take into consideration available stock during run , i mean if i run the MRP for a material with Tcode MD41 , will MRP create Planned orders , even if enough stock is available >
Thanks for coming back in advance .
Thanks and regards
Look for the MRP list as well (MD05), not only the Stock/Requirements List (MD04).
You can see there the date and time of the last MRP run, and if there was a termination that did not allow the proper run.
There may be a number of reasons why a material was not included in the MRP run, like what type of run (e.g. regenerative or net change), etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.