Off set for component requirement in PM order

Dear Experts,

In my PM order, offset date for component requirement date is working only for the first component. for the next component it is taking basic start date( i e order generated date by default) as the requirement date even though i entered offset for some days.

Experts, please explain me how to come out of this problem.

Thanks & Best regards,

Praveen

Former Member
replied

Praveen,

De-activate the user-exit and re-test. If everything works OK, then you know its the user-exit causing the problem.

Which user-exit did you use? Can you post the code?

PeteA

0 View this answer in context

Helpful Answer