Hi..

My client have a one subcontractor from which they procure 90 % of material . i have to make planning of this subcontractor seperatley. Wht are prerequisite for carrying out MRP for subcontractor.

Thnkx in advance.

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

closed

Former Member
0 Kudos

One way to is..Use special procurement key 30 ie for subcontracting ..run the MRP ..PR will be created instead of planned order..send the required materials to subcontractor and receive it after the production at subcontractor's place...

Regards,

Former Member
0 Kudos

Hi

Consider your Subcontractor as a MRP area and Plan seperately.

Jade

Former Member
0 Kudos

Best way to address is create a separate Plant for it.