Hi gurus

In my scenario

Plant A is procuring the material (suppose on 22/08/08) and sending to the Plant B on (suppose10.09.2008)

But when want to find the age the material system should calculate the ageing from 22/08

How can I do this?

Nk

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Hi,

Please refere T code MC46 to see the aging of the material.

May this will help u.

Amit

Former Member
0 Kudos

we can do it. But will required to have ABAPer. create a report from table MSEG which have all the movemnet recorded in it.

Now u have recived mat 105/101, MSEG will have the date of it Read that date in ur program in temp varable X

on that u did 301/303/305 will also have entry in MSEG. just read that date in other temp variabl Y

Now Y - X is your aging

Make a note ut selection screen of the report should have material & plant selection atleast.

Rgds