Hi,
In solar01, the BBP status is finished. Our BBP planned and actual person days are different. As I put say planned person days as 10 and actual person days as 20. The SAP automatically changes the planned person days to 20.
What is the reason that is not accepting different planned person days and actual days.
Thanks.
Anirudh,
Hi Anirudh,
this Plan person days is more an actual plan or actual forcast but an originial plan. On the basis of Plan and actual remaining days are calculated. Therefore when the task is finished, remaining days are 0 and therefor acutal plan must be equal to person days.
Regards
Andreas