Hi Gurus
in my senerio
a comp A (Channai plant)is receiving the material from china
and sending the material to other plant(hyd plant)( STO)
my question is
I want to valuate the stock
Valuation of Stocks u2013 Should be based on landed cost for all items (imported). HO should see the valuation as per landed cost.
Branch office should see the stocks as per transfer price which would be landed cost+ delta.
how i do this
N
Hi,
The material valuation depends on the valuation area.
There are two options in SAP for valuation area.It may be either company code or plant.But Plant level is recommended.
When we valuate at plant level we can valuate the materials with the landing cost in the respective valuation area.So if you see the valuation in Hyderabad plant it will be the total cost (including delta cost).And you can see the valuation in Chennai plant with the landing cost only.
Regards,
Rambhupal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.