on 09-27-2008 8:30 AM
HI,
1. when can we use update group 00018
2. suppose horizon is 1 month
1 so created today (25/9/09) --delidate (30/9/09)
2 so created today (25/9/09) --delidate cust requestedin schedule line (25/11/09) -- but due to some reason we do a early delivery on (20/10/09) -by changing actual pgi date in delivery.
3.so created today (25/9/09) --delidate (30/11/09)
pl explain in above 3 case which allwil be considered for credit check.
Delivery date - which system will consider -actual gooda issue date or deliveryd ate in schedule line in sales order
Hi,
once u r taking the update group 00018 in OVA8, obviously it will not check the delivery part.
now as u have set horizon for 1 month.so from 25/9/2008 till 24/10/2008 system will allow u take schedule line execution.once u cross this period system will stop u to move to next steps.
thanks
mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.