on 09-27-2008 8:17 AM
dear all,
when ever i m running mrp a pur req is created but my requirement is to create a pur req with item cat L.
even i m unable to change the item cat of pur req while editing it so pls tell me how to config to create pur req with item cat L after dooing mrp run.
thanks
ujwal
Dear,
You can do it with Material master settings.
Enter Special procurement = 30 - Subcontracting in MRP2 view of material.Then run MRP for material
For change material use MM02.
Regards,
Mahesh Wagh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Have you set the master data's for sub contracting process?
Following Master Data should be in place;
u2022 MM01- Material Masters for Components and FG
u2022 XK01 - Vendor Master (Subcontractor)
u2022 CS01 - BOM for FG
u2022 ME11 - Purchase Info record for Subcontracting info catergory
Me01- Source list
thanks
Prasanna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.