Hi,
I have an issue, even if the target Qty is reached , system generates schedule lines through MRP.
How can i restrict the generation of schedule line if Target Qty is reached.
Regards,
Satish.
Hi ,
1]Set u201CUnlimitedu201D field unchecked in item detail screen in SA/Contract.
2] Set Message 06067 and 06078 for Target Qty from Warning Message to Error message
3] Through Source list :remove the MRP indicator 2 from the source list.
4]Set validity date as required date in Scheduling agreement/Contract , from this date schedules will not be generated against the SA.
Thank you
Regards
Amar