I have a Bill of material ,the structure listed as below:

A(semi finished goods,F,30)

B (trading goods,F),below the A

C(phantom part,E+50),below the A

E(trading goods,F),below the C

F(trading goods,F) ,below the C

Now I want to get the A from vendor after I send E,F to him,and B is provided by vendor himself .and in sap ,I need system generate PR (purchase requirement)for A,E,and F

but no PO(planned order) generated for C,no PR for B

Now system shows to me:

1. I have given the "Y" of Item category to C and have defined C as E50(Procurement typeSpecial procurement),but still have PO generated.

2. A PR generated for B,but I need SAP ignore it,because vendor will buy it by themselves.

I think this is something like assembly subcontracting,but I am not sure is it same or not

Any advices are welcome!

Helai

Former Member
Former Member replied

Hi

goto bom of A, select item B, goto item details, next select Status/long text tab. there u can find a field called Mat prov ind. Select L (mat provided by vendor) as value in that field. System will not create PR for B.

For C in bom of A goto item details. Select special procurement 50. Keep explosion type field as blank. Run MRP system will not create PR for C

Pls revert back