Dear all,

Please help me!

here is the problem. there are several materials under the activity.

units of the materials are different. one unit is MM. the others are PC

when i use VF01, the problem appears. it states that the quanti

ty cannotbe converted from PC to MM.

You want to update the quantity 419.000 PC supplied or invoiced for thea

ccount assignment object WBS SC/BW0802-03-1.

The system found that a totals record (COSL) with unit of measure MMexis

ts for account assignment object WBS SC/BW0802-03-1. However, the quanti

ty cannotbe converted from PC to MM.

thanks a lot.