Shift Confirmation during COR6N

Hi,

How to do shift confirmation during cor6n? or during a process order confirmation.

I don't see a spot for shift, but if I put the start and finish date,

and time stamp, save.

and go to display - cort,

then I see the shift in the Personnel/ addition data.

This issue is it always comes as 1.

Is there some other way of doing shift confirmation?

I have maintained he appropriate shift sequence, - 3shifts,

assigned to the the resource.

Help will be appreciated.

Thnx!