REWORK/REPLACEMENT SCENERIO

Hi,

This is Manish. Here i am with the some jobwork rework problem. Scenerio is as follows.

1) I have some material e.g. ms sheet 12mm. & i send it to vendor for jobwork.

2) I had recieved the object from vendor i.e finish good.

3) i took GR & reconcile the challan fully.

4) Now this object goes for production purpose, where i saw that job get fractured or defective.

5) Now i want to send that job again to that vendor for rework or replacement as per agreement with vendor.But i had alrready took Gr & reconcile challan

6) So now how i could send that job to vendor & take with new or rework one without any cost.

So, is there any std. scenerio which match with above one or any procedure so that i could do above things?

If u can suggest then please go for it.Although i know this is not in fully concerned with PP but i know that u peoples can help me.

Thank in advance,

Manish