steps for discrete manufacturing in production planning module
hi,
my all dear sir, i am consused about the steps of discrete manufacturing in pp module. so please give me solution
thank you sir
surendra ashok Keerthipati replied
Hi
MM01 - make to stock with strategy 10 or 40
CS01-BOM craetion
CR01-workcentre creation
CA01-Routing cretion
MD61-Create PIR
MD04-check the requiremnt
MD02-Run theMRP against the FG
MD04 -check the planned order for the PIR
MD04-convert planned order to Production order and save the order
or you can create directly without PIR CO01
co02 -chnage order(release)
MB1A -gooda issue
CO11N-confirmation of order
MIGO -GR of order
CO02 -Teco(technical completion
CO03 -dispaly of order
-ashok