on 09-26-2008 10:02 AM
Hi Guru,
I have material A with component C1,C2,C3.
At the time of production order confirmation by using CO11N tcode, in 1st operation automatically consuming the C1 component by backflushing. After that save the confirmation.
Up to above cycle It is working fine.
As per above cycle in 1st operation at the time of confirmation it is picking the C1 some qty, But its now generate any document for Consuming of C1.
Kindly give me the soln for that
Regards,
S.Babusingh
Hi Guys,
Problem Solved.
Bcz of in MM Under Inventory management Plant parameter for the plant not maintained
Regards,
S.Babusingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check no ranges for ur material type of C1
it might be finished.
so create new no. ranges for ur documents.
Thanks & regards,
Nilesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check in MB51, enter material no C1, movement type 261 with corresponding date. Execute & check the result.
System will show the material document no which is consumed.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
111 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.