on 09-26-2008 9:58 AM
Hi masters
My requirement is to have inspector name for the inspection lot.In standard SAP we do give inspector name in QE01 for every operations.But my clients requirement they need to have inspector name for the whole inspection lot for only one time not for every operation
Regards
Mohan
HI
pl chek thsi IM setting swethere it canbe usefull
Quality Management>Quality Planning>Inspection Planning-->Define Identifier for Inspection Points
--ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohan,
For that you have to assign the your operator name in Material Master -> Under QM view -> Assign Name in QM Authorization person field.
Before That in SPRO yor have to define all your operator name follow the path.
SPRO -> QM ->Environment -> Central Functions -> Authorization Management -> Define Authorization Groups and Digital Signature -> select - Mat. Auth. Group, Insp. Lot Approval, Digital Signature and create.
It will reflect in Inspection lot header.
For further query revert.
Regards,
S.Babusingh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi do you go with manual lot creation?
i think there is no any option to go with that!
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.