Please explain the Multilevel backward scheduling in PP/DS ?
Hi,
Backward scheduling
Say FERT below HALB below ROH. FERT production time is 2days.HALB production time is 2 days.
So if you run multi level MRP, system will plan for FERT, HALB as well as ROH if stock is not available & depends on strategy.
Assume your FERT requirement on 15.10.08. Production time is 2 days, so for FERT material planned order will generate on 13.10.08.
For HALB production time is 2 days, so for that material planned order will generate on 11.10.08
Likewise for ROH also system will generate P.R
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As per my view point, you will get better response for your query if you post the same in SCM-APO Forum since it is related to PP/DS in APO.
Regards,
Tejas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.