Multilevel backward scheduling in PP/DS

Former Member
0 Kudos

Please explain the Multilevel backward scheduling in PP/DS ?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Backward scheduling

Say FERT below HALB below ROH. FERT production time is 2days.HALB production time is 2 days.

So if you run multi level MRP, system will plan for FERT, HALB as well as ROH if stock is not available & depends on strategy.

Assume your FERT requirement on 15.10.08. Production time is 2 days, so for FERT material planned order will generate on 13.10.08.

For HALB production time is 2 days, so for that material planned order will generate on 11.10.08

Likewise for ROH also system will generate P.R

Regards,

Dharma