Dear all,

what is the process to send test equipment for calibration.

ours is external calibration:

as per QM they are running the scheduling for calibration so system automatically creating one purchase requisition .

so then how to send that equipment through MM .

please give step by step

regards,

prasad

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Generally, Repair of Materials are handled via concept of Gate Pass (Returnable & Non-Returnable). But, SAP doesn't provide any option for creating Gate Pass (Returnable & Non-Returnable) in standard.

Try the below suggested procedure as a work around process;

Repair Process via Returnable Gate Pass: -

1. MM01 - Create Material Master for every Spare Part / Machinery to be sent to Vendor for Repair as Non-Valuated (Material Type "UNBW") (Do not extend Accounting and Costing views since you don't require postings of Stock value and consumption values, you only want to track the Service/Repair Charges)

It's not necessary to have materials as Non-Valuated always, it depends on your requirement.

2. MIGO - Goods Receipt > Others (Receive the quantities of these materials using Movement Type 501 / 511) - Only if Stock of Material is not available.

3. ME21N - Create Subcontracting PO (Here Main Material and Component will be same material)

4. MB1B - Transfer Posting w.r.t. Subcon PO (Mvmt Type - 541, Spare Part stock will get posted to Vendor Stock)

5. MB90 - Take Print out of this Material Doc as Returnable Gate Pass (U need to configure Message Determination of Inventory Mgmt)

6. MIGO - GR against Subcon PO (101 - Receive Spare Part, 543 O - Consumption of Spare Part form Vendor Stock)

7. MIRO - LIV for Service Charges w.r.t. Subcon PO

Note: - If PM Module is implemented then use PM Order as origin of the Repair Process. If it is not then follow the above process.

Else if you don't want to track the material stock then follow the Service Process Cycle

1. ME21N - Create Service PO (With Item Category D and Account Assignment Category K )

2. ML81N - Create Service Entry Sheet w.r.t. Service PO

3. MIRO - LIV for Service Charges w.r.t. Service PO or Service Entry Sheet

For Service Process, refer following link;

[SAP External Service Management|http://www.sap123.com/showthread.php?t=52]

Former Member
0 Kudos

Dear pankaj,

Thank u for immediate reply.

can I create Purchase order w.r.t pur.req

if yes how

regards

prasad

Edited by: prasad.k on Sep 26, 2008 12:00 PM

If service cycle to map what is the ougoing document

prasad

Answers (2)

Answers (2)

former_member192897
Active Contributor
0 Kudos

Why dont you Use Service Procurement Process??????

Former Member
0 Kudos

Dear ashok,

If we ready to use service procurement but if we create service PO what is the ougoing document for equipment.

plz reply.

regards,

prasad

Edited by: prasad.k on Sep 26, 2008 2:20 PM

plz give solution.it is urgent

regards,

prasad

Former Member
0 Kudos

Dear all,

please help some one to resolve this issue.

regards,

prasad

Former Member
0 Kudos

You can use service PO or subcontracting... Depends on how you want to map..

Reg,