The status of the Activity AALK

Activity status is AALK REL SPCF.The WBS status is REL.As a result of this we are getting the following error while running the CN30 report which is used to check Incorrect Confirmations that has occured during the daily posting of timesheets:

"System status AALK is active"

How do I go about it?

Former Member
Former Member replied

Hi

T code --CJ20N

Click on activity- EditStatus-Unlock Account assignment

Regards