hai experts,

In Training and event management ,we got through the integration part of time management there is a node specifying some percentage of attendance,

as per the documentation,i understood that,if we specify 100% at that node,if attendee had booked for 5 day event,if he has taken2 days vacation,then he is not considered as attendee.

can you please explain the functionality of that node.

Regards,

Chiran Reddy.

Former Member
Former Member replied

Hi chiran,

The Node ( Minimum % of Attendance) specifies the minimum percentage of attendance required by an Attendee to be eligible for a Business Event.

Example : 1If you specify the Minimum Percentage Attendance as 100% (Group: SEMIN, Sem. Abbr. : TIMEP) , it means that if the Attendee has taken 1 day of leave in the duration of the Business Event , he is not eligible to be booked for the Business Event. Because his attendance will not be 100 %.

Example : 2

For a 5 days Business Event :

If you specify the Minimum Percentage Attendance as 80% (Group: SEMIN, Sem. Abbr. : TIMEP) , it means that if the Attendee has taken 1 day of leave in the duration of the Business Event , he is eligible to be booked for the Business Event. Because his attendance will be 80 %, which is fulfilling our minimum eligibility.

However if the Attendee has taken 2 days leave in the duration of the Business Event , he is not eligible to be booked for the Business Event . Because the Attendance will be 60 %, i.e. less than 80 %).