on 09-26-2008 6:18 AM
Hello,
When you create schedule aggrement me31L with item type LP
then maintain Schedule line me38 then follow on function Migo .if we enter a schedule aggremnt number the system show an error "does not contain any items"
plz reply wat are the steps to follow
regards
mohan
tnx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Mohan
U can not post MIGO for Scheduling lines earlier than delivery date
i.e if delivery date of schedule line is 27.09.2008 then u can not post it today i.e 26.09.2008
either change delivery date to 26.09.2008 or wait for 27
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you getting this error in MIGO with respect to SA then just check the Delivery Date in ME38.
Del Date whould be at lease the date on which you are doing MIGO
regards
Pradeep S Yekunde
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohan,
Whenever you creating a Sch Agreement w.r.t. Contract then system will allow the quantity which is there in the Contract.
Say for example, in you contract quantity is 1000 Nos. You created 2 SA of 500 Nos.
So 1000 qty is over.
3rd time, even if you try to create a SA of 1 Qty then system system will give you an error.
This can be resolved by 2 way.
(1) Pls increase Qty the contract (ME32K).
(2) Create a new contract and create SA with respect to New Contract.
Hope this will help you.
POINTS ARE HELPFUL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You cant post GRN before the date mentioned in the delivery schedule in ME38..
PLease ensure the date mentioned in the del schedule in me38 and the GR date are same and post GRN..
Reg,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Create the PO with reference to the scheduling agreement.
Once the PO is created then go for the MIGO.Put the reference of the scheduling agreement in the PO.
Try and see.
Hope this helps.
Regards,
Prasanna.
Pls award if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Just check whether you have maintained the delivery schedule lines properly maintained in ME38 for that scheduling agreement.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.