Hi Sirs,

I have a situation where in: Whenever a delivery split happens because of two different shipping points for the different materials.

Only a single delivery should be created.And moreover the second delivery creation should not happen.

How can we do the settings so that the First delivery(For the first shipping point is created) but the second delivery for the other shipping point is not created.

I think this can be through the copy control(VTLA), but not sure.

Please help.

Monti

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

In VA02, in the overview screen, go to "Procurement" or "Shipping" tab and put the Delivery block for the particular Item.

Former Member
0 Kudos

Hi,

U can set Delivery block at line item level under shipping/procurement tab.

thanks