on 09-26-2008 3:15 AM
Hello SAPiens,
Can any one please explain, how to time phase a CVC to two different plants for two different range of dates?
Please reply your valuable views.
Thanks in advance.
Regards
Rahul Chitte
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am not sure what is your requirement.
Please note CVCs do not have a time charcateristic and as such can not be "time-phased".
You can only use Realignment to change the CVCs.