Plant Delievery time.

Hi

I am purchashing RM from different sources like Import ,Domestic & Subcontractor & leadtime are 120,30,15 days respectively.

I am using split valuation for RM.

Now which plant delivery time I have to maintain in Material Master.

hw the MRP will behave for the such case.

please give you valuable input.

rgds,

vijay