Plant Delievery time.

Former Member
0 Kudos

Hi

I am purchashing RM from different sources like Import ,Domestic & Subcontractor & leadtime are 120,30,15 days respectively.

I am using split valuation for RM.

Now which plant delivery time I have to maintain in Material Master.

hw the MRP will behave for the such case.

please give you valuable input.

rgds,

vijay

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Planned delievery time is maintained in the material master MRP-2 view & in the vendor info record. Go to ME12 and enter the material, vendor , pur org and plant

than hit enter

you will see general data screen

hit enter again and you will reach to the Pur org data 1 screen

here you can enter the pland del time on control data option.

You maintain your planned delivery times for each vendor in your info records.

You need to ensure you have flagged the scheduling info record/agreem. flag (Determine Planned Delivery Time) in transaction OPPQ.

You also need to ensure that you have maintained source list entries for your vendors that are relevant for MRP.

Now the MRP run will consider the planned delivery time in the info record and not the material master.

OR

As you have different vendors for a material, you must specify an average value. The same applies if you order the material from a fixed vendor that has varying delivery times.

Hope it will help you.

Regards,

R.Brahmankar