Hi
I am purchashing RM from different sources like Import ,Domestic & Subcontractor & leadtime are 120,30,15 days respectively.
I am using split valuation for RM.
Now which plant delivery time I have to maintain in Material Master.
hw the MRP will behave for the such case.
please give you valuable input.
rgds,
vijay
Dear,
Planned delievery time is maintained in the material master MRP-2 view & in the vendor info record. Go to ME12 and enter the material, vendor , pur org and plant
than hit enter
you will see general data screen
hit enter again and you will reach to the Pur org data 1 screen
here you can enter the pland del time on control data option.
You maintain your planned delivery times for each vendor in your info records.
You need to ensure you have flagged the scheduling info record/agreem. flag (Determine Planned Delivery Time) in transaction OPPQ.
You also need to ensure that you have maintained source list entries for your vendors that are relevant for MRP.
Now the MRP run will consider the planned delivery time in the info record and not the material master.
OR
As you have different vendors for a material, you must specify an average value. The same applies if you order the material from a fixed vendor that has varying delivery times.
Hope it will help you.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Sep 25, 2008 3:55 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.