I have a raw material of 100 tonns,with which i can make a finished goods of 54 tonnes,remaining amount would be scrap.

Finishes goods consists of two items Stator and a routor in the ratio of 2.4:1

that is 38.72 tonnes stator and 15.88 tonnes router.

Can this mapped in sap b1

replied

i think you can do it in this way:

you need 3 bills of production.

2 bills of material consist of Stator and routor, each of them in the correct ratio

(e.g. B1 = Stator [ 1xB1 = 2.4 raw material] and B2 = Routor [1xB2 = 1 raw material])

the 3rd bill of materal consists of the first and second bill of metrial

[e.g. B3 = B1 + B2, but have a look for your crap about 42 tones]

If you make a production order select B3.