Rework order trigered material no.

Former Member
0 Kudos

Hi PP Experts,

I have set trigered to create production order, But the order which is created after trigering is without material No. how i can created this with header material of confirmed production order.

Regards

sandeep

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

This is standard SAP procedure, do the confirmations for rework order & rework material will be issued from stock to order.

And GR will not be done for rework order. To get stock for reworked material do the GR for original order.

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

Pls. follow the following steps for rework order from confirmed order :

1. Create a Reference op set in tcode CA11.

Enter the plant, Description, usage and status

for the ref op set

2. Create a Standard trigger point in CO31.(Ex

Production)

Enter the Trigger Point usage /Group as FERT.

3.Tick the Trigger Point Functions.

4. Enable the indicator create order with Reference .

5.Enter the system status as PCNF.

6.The system will says standard trigger point exists from which you can

select the created Trigger Point (EXx Production)and save.

7. MD02/MD04.

8. Convert the Planned Order into Production Order and Release the order.

9 .Now confirm th ops.

10. For the last op enter the yield and rework qty

and set the status as PCNF.

11. If the status of last op is PCNF then in the

system a POP UP will appear as Activited by

Trigger Point /Create order with reference/order

number/sequence and op number which trigger point

works and enter.

12. Now a rework order will be created.

13. In c003 enter the number which is next to the actual prodn order no.Rework order will be seen.

Hope this helps.

Regards,

Tejas