on 09-25-2008 10:03 AM
Hello,
we need only one production order. And we need to schedule several GR (101) of the production order, and we need to see those dates in MD04 in order to availibity the sales order.
So, we need to save the diferents GR 101 of the production order (quantity and date)
How to do this??
Thanks
Hi!
You can't do it the way you have explained but you can plan your requirement quantities on MD61 for the material for the various GR dates. By using monthly lot size key in the material master and running the MRP you can have one planned order against all the requirement dates you have entered (which will be visible on on MD04 as planned independent requirements. Please select a suitable MTO planning strategy and make other necessary settings in material master for that strategy for your material before doing the suggested steps.
Regards,
Uday.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.