Hello All,

Partial GR update from Browser based PI Sheet - How to configure.

I have Process order for 10000 kg of Finished goods. I want to make partial GR in small quantities

I'm able to use CO60 and enter partial GR and save.

But the values are not getting populated in CO54 till i complete the PI sheet.

In tcode CO60, I can't see the option of right click ' TABLE LINE CLOSE'.

Any input will be appreciated.

Regards

Samson

Accepted Solutions (0)

Answers (1)

Answers (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi Sam,

Try it by following my replys in below mention Thread.

[Partail GR / GI through PI Sheet,|;

Regards,