Hello Experts

We have two production versions for two diffrent lines with in single plant code. How to put independent requiremnets for same material, same day but on different prod versions.

We do not know the exact distribution of quantities between the two versions; hence we cannot use quotas.

Also We want to generate shedule lines for two different storage location for same material, same vendoer & same plant during MRP run.

How we can map this requirement.