on 09-25-2008 8:44 AM
Dear guru
I have a proble in PR Release strategy
My client requirement is when he release the PR no body can change the PR .
iam trying lots of option like chengible but it is not working.
Please help me.
Thanks
Kashyap
did u try keeping changabilty option 1 for the relase indicator
regards
kunal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Go in SPRO >> Release stretegy for purchase requisition.
Here click on Release indicator.
Then enter Chagble as 1 against your indicator.
Regards,
Mahesh Wagh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try to simulate your release Strategy for PR with Release indicator as 2 - RFQ/Purchase order & assign the changeability indicator as 1 (Not Changeable after Release of PR) for your release indicator 2.
Hope it will work.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.