billing invoices get error in VFX3,Cost estimation cannot be released

Hi, All,

The following billing invoices get error in VFX3. As you know, currently cost estimation cannot be released during a month due to material ledger.

I checked T.code CK40N but requrement is with out costing run post the billing invoice with cost estimate.

Please give me advise on where is the related configaration in IMG.

Thanks

LR

Former Member
Former Member replied

Hi,

You can not post the billing document without running the Cost Estimation for the FERT Product. Because, Costing key has been assigned to FERT Material Type KE4J Settings.

Regards,

Jigar