Hi Gurus,

I have the following scenarios -

1. Release procedure should be triggered even after PR is deleted.

2. Vendor not quoting 5 times should be black listed.

Can I achieve above scenarios in standard SAP ECC 6.0? How?

I need your help.

Thanxs in advance

Regards,

Ganesh

Former Member
Former Member replied

Hi,

I dont think the first point is achievable as there is no field "deletion indicator" in structure CEBAN which is used to control release strategy.

To avoid deletion/change of PR after release you can use the Changeability Indicator 1 in line with the Release Indicators in Release strategy.This will prevent change of the document after release is done.

Regarding black listing of vendors the functioanlaity Blocking is provided by SAP which can be used in T Code XK05.However this is to be done manually.

Dhruba