Hi i have created sale order on Aug 22 and system gives confirmed date on sept 2, but its allows to create delviery and do PGI and billing also. complete cycle done in aug 28 it self, how system allows to create delivery and PGI,

pls tel me

regards

Satish

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

C there r two types of GI: one is actual another is Planned so, obvious system is allowing to create actual GI due to rescheduling of that order is activated means priority is given to others.

Yaa system in simple case follow actual GI date.

thats the reason sytem allow u to create DEl. & PGI.

Thanks

mk

Former Member
0 Kudos

closing

Former Member
0 Kudos

Hi there,

Yes manually you can pull in the delivery to create it today. In VL01N, if you give the date 2nd Sep, you can create delivery today.

It is only automatically that the delivery will be processed on the schedule line date.