Aactual work confirmation of resources

Former Member
0 Kudos

Hi,

Apart from Actual work confirmation of roles and Tasks, is it possible to enter the actual work hour confirmation of resources against staffed hours in cProject?

THANKS IN ADVANCE

Regards,

Ramesh

Accepted Solutions (1)

Accepted Solutions (1)

Konstantin
Participant
0 Kudos

Hi!

Yes, Lashan is right, it's no possible. And in CPR 4.5 too.

In cProjects, you can confirm tasks and checklist items.

Regards, Konstantin

Former Member
0 Kudos

Hi ,

Thanks for the response. It is not possible to confirm resource. Thnaks for the kind response.

Regarding,

Ramesh

Edited by: Sarvodya Team on Sep 29, 2008 3:57 PM

Answers (2)

Answers (2)

Former Member
0 Kudos

ANSWERED

Former Member
0 Kudos

Hi...

you probably wouldn't wanna hear this, but as far as I know this is not possible (upto v4.0, not too sure about 4.5). Only planning info is maintained at the resource planning and staffing level.