Batch Main Program for MPS

Former Member
0 Kudos

Hi experts,

Does someone happen to know the report RMMPS000, Batch Main Program for MPS?

What is the relationship b/w this report and the MRP planning run? Where does the reulst of this batch main program for MPS will reflect?

Thanks very much.

Regards,

Emily

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

MPS run should create the necessary PR for the stock shortage. This will be done by the program RMMPS000. Here the stocks will be directly checked at the Plant/S.Loc level and CSL would be given.

MRP log stored in MONI table to get this, we run report program RMMDMONI.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Brahmankar,

Thanks very much for your reply.

As you mention that the MPS can generate the necessary PR, could you tell where I can view the PRs? since I failed to find them in MD04.

Regards,

Emily

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Did you checked in ME5A and MD09?

Regards,

R.Brahmankar