Impliment of MRP for multiple material

Former Member
0 Kudos

Dear cons,

I want to implement MRP for multiple materials. For single material we know to use T-code u2013MD61, MD02, and MD04. We want to run MRP for multiple materials in a single transaction, so that our user will be getting benefited. Pl. provide the procedure

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For Total Planning

Use Tcode : MD01 for online planning

MDBT for Background job

Hope this helps.

Revert if any doubt.

Regards,

Tejas

Edited by: Tejas Pujara on Sep 25, 2008 7:21 AM

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

U have to define first ur MRP area >SPRO>Production>MRP > MASTER DATA > define mrp area.

Assign the storage loc.of ur material to ur MRP area.

Go in MD02 and give ur MRP area.

so u can run MRP for ur mrp area.

I thnk this will solve ur problem.

Thanx & Regards,

Nilesh Ithape

Former Member
0 Kudos

Hi,

You can use tcode MD01 to run total material for a plant.

Or with user exit M61X001, you can run MRP for

1. Specific MRP type

2. for a material type

3. For a MRP controller.

Regards,

Dharma

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

In MD61 create the requirement with Requirements Plan Number it will allow to create dement for number of material then run the MRP in MD01 with scope of planning for your plant.(OM0E)

Hope it will help you.

Regards,