Dear cons,

I want to implement MRP for multiple materials. For single material we know to use T-code u2013MD61, MD02, and MD04. We want to run MRP for multiple materials in a single transaction, so that our user will be getting benefited. Pl. provide the procedure

replied

Hi,

For Total Planning

Use Tcode : MD01 for online planning

MDBT for Background job

Hope this helps.

Revert if any doubt.

Regards,

Tejas