on 09-25-2008 6:15 AM
Dear Experts,
Can any one please tell me what is split in maintenance order and how it works? How to create split? and what is the significance of the splits?, I went through library but could not got it fully,
Any one help me in clarifying the query?
Thanks and Regards,
SAP Consultant,
It may help if you explain the problem you are having...
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
generally split come at opeartion level,
Maximum number of partial lots into which the lot is to be divided or maximum number of individual capacities where the operation is to be processed in parallel.
The number of partial lots influences the operation lead time determined in lead time scheduling since a split operation has a shorter execution time than an operation which is not split.
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
I don't think this is related to PM order. This is of Production order.
Regards,
Kaushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |