Capacity planning for loading multiple mats at same time at wrk centre

Former Member
0 Kudos

iam working for automative parts.i have asenario where iam loading both radiator assembly & CAC assembly at the same time inside the furance.

normaly sap loads capacity for radiator & CAC one after another.

Dear PP gurus pls help me how to proceed

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi

actually parellel sequece will be used if operation for a same material

but here i have two products which iam loading on the same time at furance and i have finite scheduling. it is just like mix loading in a work center.

i have also found that workcenter basic data view have one field called " mix mat" mostly u have to display this field in cr01 by allowing in field selectionin spro for work center

pls guide

byee

shamba

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Create one work center as furance with two individual capacity define in capacity tab and then do the capacity planning according to the individual capacity.

Regards,

R.Brahmankar

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Create parallel sequences in routing CA02 so thes two operation will run parallel to each other for same work center.

Regards,

R.Brahmankar

Former Member
0 Kudos

HI,

It will effect on scheduling of order.

If there is no finite capacity in work centre or shceduling profile then there will be not any effect on ur capacity.

Please revert back.

Thanks & Regards,