Dear all

Can anybody explain me how to do the sub-contracting process for below scenario

1.For FERT material i want to sub-contarcting process. (After completing this ..)

2.For FERT material i want to do again sub-contracting .

For second process excise duty is applicable in sub-contracting and bothe the process there is no need of BOM becas i m sending material and receiving material wil be same ..

Thnaks

sap-mm

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

u have to create BOM for this to do subcontracting u can keep parent and chield code same while creation of BOM

then follow regular subcontract process

Vishal...

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

u have to elaborate ur query,

u say that u r sending the fert material & receiving the same material, y u want to do sub contract process.