Hi,
Before switching from REM to discrete
1)There should not any planned order generated through REM.
2) Remove the REM check box in the material master.
3)Check the point of view also. In rem if ur using the preliminary cost estimate then switch it in to std cost estimate.
4) Create settlement profile and assign it to ur order type.
Regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Srini,
Check out this,
1. First finish all the production booking in MFBF(whether it might be Assembly backflush or component
backflush or Activity backflush) so that there's no more cancellation either through MFBF or MF41or MF12.
2.Then variance calculation & settlement of the Product cost collectors by selecting the order number that
you find it in KKF6N-->under header tab key.
3.Then setting the deletion flag for the product cost collectors.
4.Once this is done close the production version to Date,I mean set the system's date as To date,so that
it's not going to be used anymore.
5. Remove the REM profile and REM allowed indicator for all those materials which are to be shifted from
REM to Discrete.
6.You can create routing for all those materials ,if required then production version by combining the BOM
& routing.
7.If you are doing all these things at the month end it will be well and good ,so that once the new period
(month is opened) means you can take a new cost rollup for the new quantity structure.
8. If required you can create new activity type for setting the activity type+Cost center combination for
defining new activity Rates.
9.Incase if you are going to use new cost centers,then that also be implemented.
Check with this & revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Mangalraj,
we want to move from repetitive to discrete. We want to use the repetitive routings in future production orders.
Is it better to create new routings for discrete or use the existing repetitive?
What are the customizing steps in case we keep the repetitive one?
Could you please explain to me the consequences from repetitive to discrete process?
Should I follow the steps that you described higher in the discussion?
Thank in advance for you answers.
ASCM
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.