How we can restrict generation of schedule line if Target Qty is reached.

Dear Gurus,

What is the Exact Role of Target Qty in Scheduling Agreement.

I have an issue here is even if the Target Qty is reached , system generates schedule lines through MRP.

How we can restrict the generation of schedule line if Target Qty is reached.

One way is to control though source list. But this option is ok if I am handling few items. But If there are more than thousand items , then it will be difficult to remove from source list one by one .Also I have to track all those items whose target qty is over.. If u get any other way to handle this please let me know.

Please help in resolving the issue.

Thank you

regards

Amar