Collective Order - specific case

Dear All,

I would like to cancel the parent order, but the system does not permit me to do the same as a child order exists, which is logically correct. I wish to continue the production of the child order as i cannot cancel the same.

In this scenario, is it possible to complete the production of child order & on confirmation move the sub-assembly to inventory instead of issuing it onto the parent order?

If this is not possible, may i know what are the alternative ways to manage this scenario?

Edited by: Vivek on Oct 2, 2008 2:30 PM

Former Member
Former Member replied

Hello Vivek,

As you know, in collective order, the components prodced from sub order always directly posted to superior Order and not to material stock.

Still you have one option, you can post the component to stock using the Order number at MB1C with movement type 531 to one storage location.

When you look at costing point of you it is not advisable, Please chech with your Co consultant

Regards

Pradeep Kumar