regarding release strategy testing

please help me in this question. as a support consultant. I have created a configuration in release strategy of PO in dev server. after this what are testing involved and what are the next steps in transferring the file to production server. after production is it mandatory to perform user acceptance testing.

Edited by: nagarajan purushothaman on Sep 24, 2008 7:37 PM

Former Member
Former Member replied

Hi

Now release strategy needs to be checked in test server. If test cases are already available check the object with them.if test cases are not available then do the release of po considering various scenarios and see that configuration works.once test is passed then upload it in production server. user testing will help you to know if there are any road blocks so try to do user acceptance test also.