Hi,

Is it possible to load the Planned Independent Requirements based on the production version. Example one FERT is having 2 Production versions like 0001, 0002. Is there any possibility to load the demand based on the Production version 0001 and 0002. If it is possible, please explain me with details.

regards,

V. Suresh

Former Member
replied

Dear,

Yes you can select required Prod. Version With PIR itself.

To do the same follow below Path,

MD61/MD62 --- > Go to Schd. Line Tab ---> Go to Settings Menu ---> Production version.

After pressing that Tab for Prd. Version you will find Column for Prod. version gets Activated and there you can select your required Prd. Version.

System will explod the BOM and Recipe as per that Selected Prod. Version during MRP run.

Regards,

R.Brahmankar