Service Procurement with Multiple Service Line items

former_member526144
Active Contributor
0 Kudos

Dear Experts,

We have the following Business Scenario. Request your inputs in addressing this issue.

Business scenario : Most of the Procurement for our client is of services. So, we need to configure services with multiple service line items. This Shopping cart to create PR in ECC. PR to PO conversion to take place in ECC. Now onwards client needs Supplier integration for confirmation of services and sending invoices by Vendor.

Guidance required in the following

1 In Shop functionality if we select services, PR is being created in ECC with only one Service Line item. Whereas if we go for Request functionality, then always it is routing to Bidding process (which is not required for client). Can we create SC with multiple service line items with out request functionality?? Or Can we root the Request functionality with out Bidding process??

2 If we convert the PR to PO in ECC (Classic Scenario), can we go for SUS integration. In such case which is the best way of supplier integration. Can you please guide us on basic steps on installation (can we go for different client in the same server) and configuration.

Request your inputs in this regard

Thank you,

Ravi

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member526144
Active Contributor
0 Kudos

Hi,

As per SAP, SRM will not support mulitple service lineitems. But we observed some workaround solution as a standard. hope you might be knowing.

Replicate the service products from R/3 system and create a shopping cart with mulitple services(please not all are planned services) and then it results a service PO in R/3.